Inspection is the cheapest insurance in the tile trade. A container that leaves with a defect becomes a dispute that takes weeks, while the same defect caught at the loading yard takes an afternoon to fix. Here is what to check, and how to record it.

Decide the standard before you inspect

You cannot inspect against "good quality". Before production, agree in writing the grade, the tolerance for size and shade variation, and the number of tiles in a carton. Then the inspection simply tests whether the cargo matches the agreement.

If you cannot visit, a third-party inspector or your own agent in India can do the work. Send them your specification and ask for a written report with photographs.

Inspecting the cargo

Visual checks on the surface

Take cartons from several pallets, not just the top of one stack. Open them, lay tiles out on a flat surface in daylight and look for:

  • Glaze defects. Pinholes, crawling, blisters, scratches and dull patches.
  • Print faults. Misaligned digital print, banding, missing colours and blurred pattern.
  • Chips and cracks. Particularly on edges and corners.
  • Stains and marks. Handling marks, kiln deposits and dust trapped under glaze.

Look at the tile from standing height as well as up close. A defect that is invisible at arm's length may be obvious in a finished floor.

Dimensional checks

Measure length and width on a selection of tiles from each size and batch. Compare them with the nominal size and to each other. Differences between tiles show up as uneven grout lines on site.

Check squareness by laying a tile against a set square and flatness by placing a straight edge across the face and along the edges. Warping is the most common complaint in large formats. The technical details page lists the properties normally documented for each category.

Shade and batch consistency

Lay tiles from different cartons next to each other to check shade. Some variation is natural, especially in designs that imitate stone or marble, and it should be within the range agreed in advance. Confirm that cartons are marked with a batch or shade code, so installers can keep one batch on one wall or floor.

Calibre and shade are separate checks, and each should be tied to a code printed on the carton.

Packing and loading checks

StageWhat to confirm
CartonsStrong, dry, correctly printed
PalletsStable stacks, strapped, wrapped, treated wood
ContainerClean, dry, sound floor and doors
StowageNo gaps, load secured against movement
SealNumber recorded and matches the documents

Check the paperwork against the cargo

The packing list should match what is physically on the pallets: design, size, quantity and batch. A mismatch found at your port is slow and costly to fix, so catch it at loading. Ask your supplier how this check is done, and read how shipments are handled on the export page.

Record everything

Take clear photographs, label them by pallet and carton, and keep the inspection report with your order file. If a claim is needed later, dated evidence from before shipment protects both sides, and often resolves the matter without argument.

Who should inspect

You have three options: your own representative, a third-party inspection company or a visit by you. Each can work. What matters is that the inspector has your written specification, knows the agreed tolerance and reports with photographs.

Ask the inspector to check the packing and loading as well as the tiles. Many claims come from cartons that were crushed or pallets that were badly stacked, not from the tile itself.

Agree what happens if the cargo fails

Before inspection begins, agree the remedy for a failed check. Options include replacing the faulty cartons, regrading the shipment or delaying dispatch until the issue is fixed. Writing this down in advance stops an argument at the loading yard, when everyone is under time pressure and the vessel is waiting.

Lumina Tile grades tiles before packing, and a clear written standard from you makes that grading easier to match to your expectations. The more precisely you describe an acceptable tile, the less room there is for misunderstanding.

Common questions

How many cartons should be opened?

There is no single figure that suits every order. Agree a checking plan with your supplier or inspector based on the order size and the number of designs, and apply it consistently.

Is third-party inspection worth it?

For a first order, a large order or a new supplier, yes. An independent report gives you evidence and a neutral view.

What if I find a defect after loading?

Stop dispatch, document the issue and agree the remedy in writing before the container sails. Replacing cartons at the yard is far easier than resolving a claim overseas.

If you want an inspection built into your order, tell Lumina Tile your grade and tolerance requirements and we will confirm how they are checked before dispatch.